Featured Projects
Project: Monroe Correctional Complex
Recreation Yard Improvement
Monroe, WA
Client: Washington Department of Corrections
Description: Improving recreational areas in high-security units. Project included concrete cutting, roof demolition, window grill installation & roof grill installation.
Completed: August 2019
Project Cost: $495,975
Project: Woodburn Museum & Theater Seismic Upgrade
Woodburn, OR
Client: City of Woodburn
Description: Seismic upgrade of Historic building, roof replacement plus skylight to the Museum and Theater building.
Completed: July 2019
Project Cost: $270,645
Project: Department of Social & Health Services Kelso Lobby Renovations
Kelso, WA
Client: Washington DSHS, Olympia, WA
Description: Tenant Improvement entailed revisions of restrooms, office space, exterior painting, and parking lot striping.
Expected Completion: October 2019
Project Cost: $221,012
Project: Joint Base Lewis-McChord (JBLM)
Client: Veterans Construction Enterprises, LLC
Lakewood, WA
Description: Repairing structural members in trusses throughout an active maintenance building, Stitch Bolting Added structural reinforcement to nearly 3,000 locations to bolster truss system in maintenance building. Use of Aerial Work Platforms & Fall Protection Equipment to access hard-to-reach locations.
Completed: December 2018
Project Cost: $883,557
Project: On Call Carpentry and Door Installation Services, Harborview Medical Center, Seattle, WA
Client: UW Medicine Supply Chain
Description: Replaced over 600 doors, including over 150 doors in Psychiatric Ward at Harborview Medical Center
Completed: Spring 2018
Project Cost: $770,894
Project: Ft Vancouver Post Cemetery Headstone Realignment and Cleaning
Vancouver, WA
Client: US Army Corps of Engineers Seattle District, Seattle, WA
Description:Realigned, raised, and cleaned 1450 upright marble headstones, turf repair.
Completed: Sept 2018
Project Cost: $288,293